Crews completed three houses along S 69th St. this week.
Next week's work will be to complete the three remaining houses on S. 69th Street from James Avenue to La Vista Drive.
The intersection of S 70th Street and S 69th Street will be closed Monday during the day for concrete breaking operations and then reopened to residential traffic. It will close again on Tuesday morning and remain closed until Thursday for storm sewer repair work, then an aggregate surface course will be installed temporarily.
The area between James Avenue and S 70th Street will be closed to traffic on Monday for the final lateral service repair in that area, then reopened at end of the day.
Wednesday (potentially pending storm sewer completion), Thursday and Friday work will be concentrated at the intersection of S 69th Street and La Vista Drive.
There will be a crew in over the weekend doing saw cutting operations on La Vista Drive from Florence Street to S. 69th Street in preparation of work progression.