News Flash Home
The original item was published from 7/24/2023 10:29:31 AM to 8/1/2023 12:00:05 AM.

News Flash

East La Vista Sewer Project

Posted on: July 24, 2023

[ARCHIVED] July 24 East La Vista Update

Here is your Monday update: 


Crews are continuing with lateral repair work on Josephine. Today (Monday) and possibly tomorrow (Tuesday) concrete will be poured in the areas of the service lateral repairs on northbound La Vista Dr. The southbound lane will be poured on Friday. Sections of Josephine between 72nd St. and La Vista Dr. will also receive new concrete this week as well. 


MUD is working on Josephine to relocate the fire hydrants, which will require water service to be shut off for a short time today (Monday) and from 7 a.m.-1 p.m. tomorrow (Tuesday) for them to remove and reinstall the new hydrants. This will affect people on La Vista Dr. from Florence to Harrison and a few houses on Josephine.

 

Have a great week and watch for another update on Friday, July 28. 

Facebook Twitter Email